Sales Mix and Product-Mix Optimization
Quick answer. Contribution per machine hour = (selling price − variable cost) ÷ machine hours per unit. Rank products by it and make the highest first, up to demand. In the illustrative example below, product B (€30 of contribution, 0.5 hours) earns €60 per machine hour against €40 for product A (€48, 1.2 hours), so B goes first and the mix earns about €110,000 a month instead of €96,000.