Every tier two and tier three supplier I have worked with in the automotive chain has the same letter in a drawer. It comes from the OEM or the tier one above them, it arrives once a year, and it says that the price of every part number on the schedule will fall by an agreed percentage from the first of January. The letter does not ask which part numbers can bear it. It cannot, because the customer does not know, and in most of the suppliers I have seen, neither does the supplier. The standard cost per part carries setup, quality and logistics as a percentage of material or a rate per machine hour, which means the price-down is answered with an average, and an average is the one thing a plant with eight hundred live part numbers cannot afford to negotiate with.
How should a tier two or tier three automotive supplier cost setup, quality and logistics by part number?
Treat each production cell, each inspection resource and each logistics resource as a pool with a capacity cost rate per minute, and write a time equation for the three things a part number consumes beyond its run time: changeover minutes per lot, inspection and sorting minutes per lot and per nonconformance, and handling minutes per call-off, per pallet and per returnable container loop. Multiply by the lots, call-offs and nonconformances each part number actually generated in a closed quarter, and the cost per unit separates by an order of magnitude between a high-volume part run in large lots and a service part run twelve times a year in lots of five hundred. That separation is what lets a supplier answer the annual price-down part number by part number instead of across the board, and it also makes visible the capacity held for volumes the customer forecast and did not order.
What the standard cost hides in this chain
A supplier’s standard cost is usually built for the quote and for inventory valuation, and it does both jobs adequately. The run time on the press, the moulding machine or the assembly cell is measured; the material is priced; and everything else, changeovers, quality, packaging, EDI, milk runs, premium freight, the customer’s audits and the PPAP file, sits in an overhead rate applied per machine hour or as a percentage on top. The rate is right in total, because it reconciles to the ledger, and wrong for almost every individual part number, because none of those costs is driven by machine hours. A changeover is driven by the lot. A sort is driven by the nonconformance. A pallet label is driven by the call-off. A part number that runs twelve times a year in small lots consumes twelve changeovers and twelve sets of paperwork; a part number that runs twice a year in a lot that fills the cell for a week consumes two. The machine-hour rate charges both in proportion to their run time, which is the one quantity the two parts have in common. The manufacturing cost allocation page covers the general mechanism; what follows is the automotive-specific version.
The three time equations
Setup. Changeover minutes per lot depend on what is changing: a tool change on a press is not the same as a colour change on a moulding machine, and a change between two parts of the same family is faster than a change across families. A time equation for the cell captures this as a base time plus terms for tool change, material change, colour change and first-off approval, with the coefficients measured from the cell’s own changeover log or from a fortnight of timing. The setup and changeover cost page has the arithmetic for a single cell; the automotive difference is that the lot count per part number is dictated by the customer’s call-off pattern and the supplier’s own inventory policy, so the number of setups is partly the customer’s decision and partly yours, and both should be visible.
Quality. The quality cost of a part number is a set of minutes and a set of events: incoming inspection per delivery of material, in-process checks per lot, final inspection per lot, and then the events that make the difference, a nonconformance report, a sort at the customer’s plant or at the supplier’s, a rework loop, an eight-discipline report, a containment action. Each is minutes of somebody’s capacity and often external cost as well. The part numbers that generate most of them are rarely the high-volume stable ones; they are the recent launches, the ones with a tight tolerance the process barely holds, and the ones with an unresolved supplier issue upstream. Charging quality as a percentage on every part spreads the cost of the difficult parts across the easy ones, and the easy ones are the ones the price-down should be discussed on. The cost of quality page describes the categories; the point here is to attach each event to the part number that caused it.
Logistics. A call-off generates a schedule line, a pick, a pallet or a set of containers, a label, an advance shipping notice and a slot on a truck. A returnable container has a loop, and a loop has a cleaning, a count and a loss rate. A part number delivered daily in small quantities to a just-in-sequence line consumes hundreds of these events a year; one delivered monthly consumes twelve. Premium freight, the air shipment or the dedicated van when the schedule slipped, is the most visible logistics cost and usually the smallest in total; the handling minutes are the large one and the least visible. The cost-to-serve in logistics page and the cost driver library list the drivers most suppliers already record in their WMS and EDI systems without using them.
An illustrative cell, with invented numbers
Take one press cell costing 600,000 euros a year all in, people, machine, tooling maintenance, floor space and the share of the plant’s indirect staff that a reconciliation puts on it. Practical capacity, after breaks, planned maintenance and a realistic allowance for unplanned stops, is 4,800 hours, which gives a capacity cost rate of 125 euros an hour, or about 2.08 euros a minute. Every number here is invented for the illustration and the arithmetic has been checked.
Part A runs 200,000 units a year in twenty lots of 10,000. Each changeover takes 90 minutes. Twenty changeovers are 1,800 minutes, which at 2.08 euros a minute is 3,750 euros a year, or just under two cents per unit. Part B is a service part for a platform that went out of production: 6,000 units a year in twelve lots of 500, same tool family, same 90-minute changeover. Twelve changeovers are 1,080 minutes, 2,250 euros a year, and 37.5 cents per unit. The standard cost applies the same overhead to both, because it charges by run time. On setup alone, Part B costs twenty times more per unit than Part A, and that is before its quality and logistics events, which for a service part with a low-volume, irregular call-off pattern are usually worse, not better.
When the price-down letter arrives, the supplier who knows this can say: Part A can take the percentage, and we will look at lot sizes to fund it; Part B cannot, and the price should rise or the minimum lot should be 2,000. The supplier who does not know this gives the percentage on both and finds out three years later, from the plant’s margin, which was which.
The capacity the customer forecast and did not order
A part is quoted at a volume. The customer’s forecast at nomination was, let us say, 250,000 units a year, and the supplier bought the tool, staffed the cell and sized the container loop for that. The actual call-offs, over the programme’s life, come in at 160,000. The cell’s capacity was held for the forecast; the cost of the difference is real and it belongs somewhere. In a standard cost it is under-absorbed overhead, which the plant’s variance report shows as a single number nobody can act on. In a TDABC model it is the unused capacity of that cell, in minutes and in euros, attributable to the programme whose forecast created it. That is not a number to hide inside the part price. It is a number to put on the table when the price-down is discussed, because the customer’s forecast is what created the cost, and most OEM purchasing contracts have a clause about volume shortfall that nobody invokes because nobody has the figure. The cost of unused capacity page explains the reporting; the article on variance analysis in TDABC shows how it replaces the absorption variance with something a plant manager can read.
The long tail of part numbers
A supplier with several hundred live part numbers usually has a distribution that looks the same everywhere I have measured it: a few dozen part numbers make most of the volume and most of the profit, a broad middle roughly covers its cost, and a tail of service parts, low-volume variants, colour options and parts for a customer who is winding down consumes setups, quality events and call-offs out of all proportion to its revenue. The SKU profitability page shows the shape as a whale curve; in automotive the tail is often contractually locked, because service-part supply obligations run for years after the platform ends, so the response is rarely to drop it. The response is to price it, to batch it, or to negotiate an annual service-part settlement instead of a per-piece price, and none of those conversations can start without the cost per part number.
Answering the letter
The annual price-down is a commercial fact of the chain and I do not suggest a tier three supplier can refuse it. What the cost per part number changes is the shape of the answer. Instead of a percentage across the schedule, the supplier can propose a percentage on the stable high-volume parts, funded by named lot-size or packaging changes the customer can help with; a hold or an increase on the tail, with the setup and call-off arithmetic attached; a volume-shortfall claim on programmes running well below nomination; and a quality surcharge or a joint containment plan on the part numbers that generate the sorts. Purchasing at the tier one or the OEM has seen this argument before and does not always accept it, but in my experience the supplier who brings the arithmetic gets a different conversation from the supplier who brings a complaint. The manufacturing pricing page and the article on should-cost with time equations are relevant, because the customer’s should-cost model is built the same way and it is better to hold the same kind of numbers than to argue against them with an average.
The price-down letter asks one question of every part number. Only a cost model that separates setups, quality events and call-offs by part number can give a different answer for each.
Where to start
One plant, one closed quarter, the cells as cost pools with practical capacity, and three time equations: changeover per lot, inspection and sorting per lot and per nonconformance, handling per call-off and per container loop. The lot counts come from the MES or the production orders, the nonconformances from the quality system, the call-offs from the EDI log; none of it needs new data collection. Reconcile the pools to the quarter’s ledger, run the equations against the part numbers, and rank the schedule by cost per unit against price. The ranking is the negotiating document for the next letter, and the TDABC in manufacturing page describes the model that produces it. The article on manufacturing margins under tariff volatility covers the other letter that arrives some years, the one about duties, with the same logic.