Variance analysis is taught in pieces. Materials one week, labour the next, overhead in a chapter of its own with its two-way, three-way and four-way splits, and sales variances somewhere near the end, usually on a different company with different numbers. The pieces are fine. What students almost never see is all of them on one set of data, added up, and shown to explain exactly the gap between the profit that was budgeted and the profit that was made. That is the whole point of the exercise, and it is the thing an exam question with the words “prepare an operating statement” is really asking for. Here is one company, one period, every variance, and a reconciliation that closes to the euro.

In brief

How do the materials, labour, overhead and sales variances fit together?

They are the pieces of one number: actual profit minus budgeted profit. In the example below the budget was €290,000 and the actual result €291,080, a total variance of €1,080 favourable. That small number is the net of much larger ones pulling in opposite directions: an €8,600 adverse sales price variance, a €19,000 favourable sales volume variance (itself €7,400 of mix and €11,600 of quantity), €15,480 adverse on materials, €1,640 adverse on labour, and €7,800 favourable on overhead, which the three-way split shows as €8,800 adverse spending, €1,600 favourable efficiency and €15,000 favourable volume. Every variance is computed below from the same standards and the same actuals, and the operating statement at the end adds them back to €291,080.

The company, the standards and the budget

A workshop makes two sizes of steel storage rack, R1 and R2. Both use the same steel, bought by the kilogram, and the same grade of assembly labour, paid by the hour. Variable and fixed overhead are absorbed on direct labour hours. The standard cost cards for the period are:

Per unit R1 R2
Direct material at €2.50 per kg 8 kg, €20.00 12 kg, €30.00
Direct labour at €16.00 per hour 1.5 h, €24.00 2.5 h, €40.00
Variable overhead at €4.00 per labour hour €6.00 €10.00
Fixed overhead at €10.00 per labour hour €15.00 €25.00
Standard cost €65.00 €105.00
Standard selling price €90.00 €140.00
Standard profit per unit €25.00 €35.00

The budget for the period was 6,000 R1 and 4,000 R2, which is 10,000 units in a 60:40 mix. That volume needs 6,000 times 1.5 plus 4,000 times 2.5, which is 9,000 plus 10,000, so 19,000 standard labour hours. The fixed overhead budget is €190,000, and dividing it by the 19,000 budgeted hours is where the €10.00 fixed overhead absorption rate on the cost card comes from. The variable overhead budget is 19,000 times €4.00, €76,000. Budgeted profit is 6,000 times €25.00 plus 4,000 times €35.00, which is €150,000 plus €140,000, so €290,000. As a check, budgeted revenue is €540,000 plus €560,000, €1,100,000, and budgeted cost is €390,000 plus €420,000, €810,000; the difference is the same €290,000.

What actually happened

Production equalled sales, so there is no stock movement to complicate the reconciliation. The actuals for the period:

Actual Amount
R1 made and sold 5,500 units at €92.00, revenue €506,000
R2 made and sold 4,900 units at €136.00, revenue €666,400
Total revenue €1,172,400 on 10,400 units
Steel bought and used 104,000 kg at €2.62, €272,480
Labour paid and worked 20,100 hours at €16.40, €329,640
Variable overhead €83,200
Fixed overhead €196,000
Total cost €881,320
Actual profit €291,080

Two derived figures are used by almost every variance below, so compute them once. The standard quantity of steel allowed for what was actually made is 5,500 times 8 plus 4,900 times 12, which is 44,000 plus 58,800, so 102,800 kg. The standard hours allowed are 5,500 times 1.5 plus 4,900 times 2.5, which is 8,250 plus 12,250, so 20,500 hours. The word “allowed” matters: these are the inputs the standards permit for the actual output, not the budgeted inputs. Comparing actual usage against the budget’s 19,000 hours would mix a volume effect into an efficiency measure.

Materials: price and quantity

The price variance is the difference between standard and actual price, on the actual quantity bought: (€2.50 minus €2.62) times 104,000 kg, which is €0.12 times 104,000, so €12,480 adverse. Steel cost 12 cents a kilo more than the standard assumed. Because the workshop bought exactly what it used, the price variance is the same whether it is isolated at purchase or at usage; when purchases and usage differ, the exam convention is to take it at purchase, on the quantity bought.

The quantity variance (also called usage) is the difference between the standard quantity allowed and the actual quantity used, at standard price: (102,800 minus 104,000) times €2.50, which is 1,200 kg over the allowance, so €3,000 adverse. Note that it is priced at the standard €2.50 and not the actual €2.62, so that the two variances do not overlap: the 1,200 excess kilos at 12 cents extra are already inside the price variance.

Together, €15,480 adverse. Check it against the totals: the standard material cost of actual output is 102,800 times €2.50, €257,000, and the actual material cost was €272,480; the difference is €15,480. Every pair of variances in this article can be checked that way, and in an exam it is worth the thirty seconds.

Labour: rate and efficiency

The rate variance is (standard rate minus actual rate) times actual hours paid: (€16.00 minus €16.40) times 20,100, so €8,040 adverse. The efficiency variance is (standard hours allowed minus actual hours worked) times the standard rate: (20,500 minus 20,100) times €16.00, which is 400 hours saved, so €6,400 favourable. Hours paid and hours worked are the same here, so there is no idle time variance; when they differ, the idle hours times the standard rate come out as a separate adverse variance and the efficiency variance is measured on hours actually worked.

Net, €1,640 adverse. Check: standard labour cost of actual output is 20,500 times €16.00, €328,000, against €329,640 actual. The story is a common one: a more expensive crew that works faster. The rate variance and the efficiency variance are two views of the same decision, and reading them separately, as if a purchasing manager owned one and a supervisor the other, misses that.

Overhead: four ways, three ways, two ways

Overhead variances confuse people because the same total can be cut into two, three or four pieces, and textbooks name the pieces differently. Start from the four-way split, which keeps variable and fixed overhead apart, and then merge.

Variable overhead spending variance. What variable overhead should have cost for the hours actually worked, minus what it did cost: 20,100 hours times €4.00 is €80,400, against €83,200 actual, so €2,800 adverse. It is measured on actual hours, not standard hours, because variable overhead is assumed to be incurred as hours are worked; the efficiency effect is separated next.

Variable overhead efficiency variance. (Standard hours allowed minus actual hours) times the variable rate: 400 hours times €4.00, so €1,600 favourable. It is the labour efficiency variance’s shadow: the same 400 hours, at €4.00 instead of €16.00.

Fixed overhead spending variance (also called expenditure or budget variance). Budget minus actual: €190,000 minus €196,000, so €6,000 adverse. No hours enter this one. Fixed overhead does not flex with activity, so the only question is whether the amount spent matched the amount budgeted.

Fixed overhead volume variance (production-volume variance). Fixed overhead absorbed into production minus fixed overhead budgeted: 20,500 standard hours times €10.00 is €205,000 absorbed, against a budget of €190,000, so €15,000 favourable. Equivalently, (20,500 minus 19,000) times €10.00. This is the variance students most often misread. It is not money saved. It says that because output ran 1,500 standard hours above the level the €10.00 rate was built on, the absorption rate recovered €15,000 more fixed cost than exists, and the cost accounts had over-absorbed by that amount. It is an artefact of absorption costing, and under marginal costing it does not exist.

The four-way total is 2,800 adverse plus 1,600 favourable plus 6,000 adverse plus 15,000 favourable, which is €7,800 favourable. Check: overhead applied to production is 20,500 hours times (€4.00 plus €10.00), €287,000, against actual overhead of €83,200 plus €196,000, €279,200. The difference is €7,800.

The three-way split merges the two spending variances: spending €2,800 plus €6,000, so €8,800 adverse; efficiency €1,600 favourable (variable overhead only, since fixed overhead has no efficiency component in this convention); volume €15,000 favourable. The two-way split merges everything except volume into a flexible-budget or controllable variance: €8,800 adverse plus €1,600 favourable, so €7,200 adverse; and volume €15,000 favourable. The one-way analysis is the total, €7,800 favourable. Whichever split the question asks for, the pieces sum to the same €7,800, and a set of overhead variances that does not is wrong somewhere.

One more convention, common in UK and Commonwealth syllabuses: the fixed overhead volume variance is itself split into a capacity variance, (actual hours minus budgeted hours) times the fixed rate, which is (20,100 minus 19,000) times €10.00, €11,000 favourable, and a fixed overhead efficiency variance, (standard hours allowed minus actual hours) times the fixed rate, 400 times €10.00, €4,000 favourable. They add to the €15,000. The capacity piece says the workshop worked 1,100 more hours than budgeted; the efficiency piece says it got 400 hours more output from those hours than the standard expected. In the US three-way convention above, that €4,000 stays inside the volume variance and the efficiency line carries only the variable part.

Sales: price, then volume into mix and quantity

The sales price variance is (actual price minus standard price) times actual units, product by product. R1: (€92.00 minus €90.00) times 5,500, €11,000 favourable. R2: (€136.00 minus €140.00) times 4,900, €19,600 adverse. Total €8,600 adverse. The workshop got more for the small rack and gave away more on the large one.

The sales volume variance under absorption costing is (actual units minus budgeted units) times the standard profit per unit, because the effect of selling one more unit at standard price and standard cost is one more unit of standard profit. R1: (5,500 minus 6,000) times €25.00, €12,500 adverse. R2: (4,900 minus 4,000) times €35.00, €31,500 favourable. Total €19,000 favourable. (Under marginal costing the same variance is valued at standard contribution, €45.00 and €60.00 here, and there is no fixed overhead volume variance to go with it; the two conventions reach the same actual profit by different routes.)

That €19,000 mixes two things: the company sold 400 more units in total, and it sold them in a different proportion from the budget’s 60:40. To separate them, ask what the actual total of 10,400 units would have looked like in the budgeted mix: 60 percent of 10,400 is 6,240 R1 and 40 percent is 4,160 R2.

The sales mix variance compares actual units with actual total at budgeted mix, at standard profit. R1: (5,500 minus 6,240) times €25.00, which is 740 units short, €18,500 adverse. R2: (4,900 minus 4,160) times €35.00, 740 units over, €25,900 favourable. Total €7,400 favourable. The 740 units that moved from R1 to R2 each carried €10.00 more standard profit, and 740 times €10.00 is €7,400.

The sales quantity variance compares actual total at budgeted mix with the budget, at standard profit. R1: (6,240 minus 6,000) times €25.00, €6,000 favourable. R2: (4,160 minus 4,000) times €35.00, €5,600 favourable. Total €11,600 favourable. The short cut confirms it: the budgeted weighted average profit is €290,000 over 10,000 units, €29.00 a unit, and 400 extra units at €29.00 is €11,600. Mix plus quantity, €7,400 plus €11,600, gives back the €19,000 volume variance.

€1,080
favourable, the total variance: actual profit €291,080 against a budget of €290,000
€7,800
favourable total overhead variance, cut into 2, 3 or 4 pieces that always add to the same number
740
units that moved from R1 to R2 in the mix, each carrying €10.00 more standard profit: the €7,400 mix variance

The reconciliation, from budgeted profit to actual profit

Now lay every piece on one statement. Favourable variances are added, adverse ones subtracted. The order below is the standard one: sales volume first, to arrive at the standard profit on what was actually sold; then sales price; then the cost variances, to arrive at what was actually earned.

Operating statement for the period € €
Budgeted profit 290,000
Sales quantity variance 11,600 F
Sales mix variance 7,400 F 19,000 F
Standard profit on actual sales (5,500 x 25 + 4,900 x 35) 309,000
Sales price variance (8,600) A
300,400
Material price (12,480) A
Material quantity (3,000) A
Labour rate (8,040) A
Labour efficiency 6,400 F
Variable overhead spending (2,800) A
Variable overhead efficiency 1,600 F
Fixed overhead spending (6,000) A
Fixed overhead volume 15,000 F
Total cost variances (9,320) A
Actual profit 291,080

It closes. €290,000 plus €19,000 is €309,000; minus €8,600 is €300,400; minus €9,320 of net cost variances is €291,080, which is the actual profit computed directly from revenue of €1,172,400 and costs of €881,320. The sum of every variance on the page, €19,000 favourable minus €8,600 minus €9,320, is the €1,080 favourable total variance. If your statement does not close, the fault is almost always one of three: a volume variance measured against budgeted hours instead of standard hours allowed, a quantity or efficiency variance priced at actual instead of standard, or a sales volume variance valued at price instead of profit.

The total variance was €1,080. Nobody would have noticed. Underneath it, sales lost €8,600 on price, steel cost €15,480 more than it should, and a mix shift and a volume gain covered for both. The reconciliation is not the answer; it is the table of contents for the questions.

What the exam does not ask, and what a plant would

Every variance above is correct and every one of them is a question rather than a conclusion. The €15,000 favourable volume variance is the clearest case. It looks like the largest good news on the page, and it is nothing of the kind: it is the arithmetic consequence of absorbing a fixed cost through a rate built on a volume that turned out to be wrong. Had the workshop produced fewer hours than budget, the same line would have read adverse, with the same fixed cost and the same building. A plant that reads its volume variance as performance will schedule production to make it favourable, which is how warehouses fill. The way out of that trap is to stop dividing fixed cost by budgeted volume and divide it by practical capacity instead, so that the gap becomes the cost of unused capacity, a number with a plain meaning; that is the step from standard costing towards time-driven activity-based costing, and it is the subject of the over- and under-absorption article.

The second thing a plant would ask is who owns what. The materials price variance belongs to purchasing only if purchasing chose the supplier; if the more expensive steel was the only grade that would hold the tighter tolerance the customer asked for, it belongs with the sales price variance that the customer paid for it. The labour rate and efficiency variances are one decision seen twice. And the €7,400 favourable mix variance is only good news if R2’s extra €10.00 of standard profit survives the costs the standard cost card does not see: the larger rack takes more setups, more warehouse space and more freight per unit, none of which is absorbed on labour hours. Learn the mechanics completely, because an operating statement that closes is the entry ticket to the conversation. Then learn what the standards left out.