When a construction project goes over budget, the first explanation is usually quantities: more concrete than measured, a design change, a subcontractor who priced too low. Those things happen. But a cost model often tells a different story. A large part of what a project costs is not driven by what is built but by how long it takes to build it, and most estimates price the first far more carefully than the second.

What matters here

Why do construction projects overrun?

Often because time costs money and the estimate treats it as a fixed line. Site management, cranes, scaffolding, site facilities, security and temporary services are paid by the week. When the programme slips, those costs grow with every extra week, even if the quantities built stay close to the estimate. A cost model that separates quantity driven costs from time driven costs shows which part of an overrun came from building more and which part came from building for longer.

Why the estimate and the final cost drift apart

A typical estimate is built from quantities: measured items multiplied by rates, plus subcontract packages, plus a percentage for preliminaries and overhead. That structure is good at capturing what will be built. It is weak at capturing duration, because the site overhead is often entered as a total or as a percentage of the direct cost, not as a cost per week multiplied by a planned number of weeks. When the project runs late, the estimate has no line that moves with the delay, so the extra cost appears at the end as an unexplained overrun rather than as a known consequence of each week lost.

Two kinds of cost inside every project

The first kind follows quantities: materials, plant hired per unit of work, subcontract packages priced per measured item, labour that is paid for output. If the quantities hold, this cost holds. The second kind follows time: the site team, the site office and welfare facilities, cranes and hoists on weekly hire, scaffolding, temporary power, security, insurance for the duration and the share of head office support assigned to the project. This cost runs every week the site is open, whatever is being built that week. Keeping the two apart, with the second expressed as a weekly rate, is the step that turns an overrun from a surprise into something that can be explained and managed.

A worked illustration

The figures below are hypothetical, chosen only to show the arithmetic. A project is estimated at 800,000 of quantity driven cost. Site overheads run at 10,000 per week and the programme is 20 weeks, so the time driven cost is 200,000 and the budget is 1,000,000. The contract price is 1,150,000, which leaves a planned margin of 150,000. On completion, quantity driven costs come in at 820,000, slightly above the estimate. The project finishes in 26 weeks instead of 20, so site overheads reach 260,000. The final cost is 1,080,000, an overrun of 80,000. Of that overrun, 20,000 comes from quantities and 60,000 from time, which is 75% of the total. The margin falls from 150,000 to 70,000, and most of the fall came from six extra weeks on site, not from building more than was planned.

80,000
total overrun on the project in the illustration, against a budget of 1,000,000
60,000
part of the overrun caused by six extra weeks of site overheads
75%
share of the overrun driven by time rather than by quantities

Where project cost control goes wrong first

The first mistake is reporting cost against budget only by cost code, which shows that preliminaries are over without showing why. The second is tracking progress by value of work done and treating the site overhead as a fixed sum spread over that value, which hides the weekly burn until the final account. The third is pricing variations and design changes by their quantities alone, without adding the extra time they cause on site. Each of these leaves the time driven cost without an owner, so delays are discussed as a programme problem and their cost appears only when it can no longer be recovered.

A week of delay has a price. If the estimate cannot tell you what it is, the final account will.

What to put in place first

Split the estimate into quantity driven and time driven costs, and express the second as a weekly rate for each phase of the programme. Report actual cost against both every month: quantities against measured progress, time driven cost against weeks elapsed. When the programme moves, recalculate the time driven cost straight away and show it as the cost of the delay. Price every variation with both parts, the work itself and the time it adds. Over several projects, the same model shows which types of work, phases or contract forms tend to run long, which is the information needed to price the next tender with a realistic duration.

Find out where cost and margin are slipping before the next project starts.

The Profit Check is a short diagnostic that shows where cost and margin are likely to be hiding in your business, and which questions to ask first.

Take the Profit Check

Related reading: project costing in construction and engineering.